Court Strikes Down Key Provisions in FY26 CoC NOFO
By: Steven Molinari, Policy Analyst
November 24, 2026 — On Friday, the U.S. District Court for the District of Rhode Island ruled in favor of the plaintiffs in National Alliance to End Homelessness v. HUD, finding that HUD exceeded its statutory authority and violated federal law as it relates to the fiscal year 2026 Continuum of Care Notice of Funding Opportunity (FY26 CoC NOFO).
The court provided justification, noting that several key provisions in the FY26 CoC NOFO were unlawful in that they imposed funding criteria that prioritized the administration’s policy agenda over the requirements established by Congress. Specifically, the court addressed HUD’s $1.3 billion set-aside for transitional housing (TH) and supportive services only (SSO) projects noting that this provision in the NOFO is vacated, severed, and declared unlawful.
According to court documents, HUD cannot apply any funding priority rule or policy that categorically prioritizes TH, SSO, or new projects over existing or permanent housing projects in implementing the 2026 NOFO.
Tier 2 Funding Applications To Be Reopened
The court has ordered that HUD reopen and allow CoCs to resubmit applications for Tier 2 funding until 11:59pm ET on December 1, 2026. However, as of now, it appears that submitting an application on the Grants.gov website for this NOFO is unavailable.
Funding award announcements for Tier 2 projects must be made by no later than December 31, 2026.
It is unclear if HUD plans to challenge this decision, however, specific objections to this order may be submitted to the court by HUD or the plaintiffs by today.
The order is not expected to delay the announcement of Tier 1 awards that are set to be announced by December 1, 2026.
NAHRO will continue to monitor the situation, including any changes to CoC award funding that result from future court decisions or HUD actions.